Beyond the Solar Business Case: Making Energy Investment Deliver Enterprise Value
Share this post
Executive perspective | November 2026
Imagine two facilities on the same industrial estate. One runs a packaging line through the working day. The other dispatches refrigerated stock before sunrise. Each has enough roof space for the same solar array. At the packaging plant, a sunny Tuesday can displace hours of purchased electricity. At the depot, the most valuable hour may be the one before dawn when the refrigeration and loading systems must stay online. A proposal based on roof area and annual electricity spend could recommend identical investments for both.
What must the investment deliver?
Before inviting bids, ask the executive sponsor to complete one sentence: “We will spend this money so that this part of the business can achieve this outcome, under these conditions.” For the plant, that might mean lowering electricity cost per saleable unit through a shift change. For the depot, it might mean keeping specified cold rooms within temperature limits during a two-hour interruption. These briefs lead to different designs, financial tests and measures of success.
Agree which outcomes are requirements and which can be traded. If continuity is essential, screen out options that cannot meet the required load and duration. Then compare the cost and carbon performance of the qualifying options. This avoids assigning an attractive financial score to a design that cannot do the job.
The decision for the board
Approve a defined operating outcome, the capital or contractual commitment needed to secure it, and the evidence management will bring back. A generation forecast can support that decision. It cannot tell the board whether a facility will still need the power in five years, who carries the risk if it does not, or who can claim the environmental benefit.
Start with the operating day
Ask operations for a year of interval meter data alongside invoices, shift rosters, shutdowns and outage logs. Reconcile the meter totals to the bills and mark estimated or missing intervals. Plot a normal weekday, a weekend and a seasonal peak. Overlay expected solar production. The overlap identifies electricity the site can use immediately. Surplus needs a credible destination and an agreed price before it earns a place in the cash flow.
Walk the site with the person accountable for production. Which loads can move to midday? Which must restart together after a trip? At a leased site, who owns the roof, pays the electricity bill and receives the savings? A landlord funding a system while tenants retain the full bill saving faces a different investment decision from an owner-occupier.
Compare options against the same operating brief
Efficiency and scheduling. Test chiller controls, maintenance and movable loads first. Recalculate demand after those changes before sizing generation. Otherwise the same electricity saving can appear in two proposals.
On-site solar. Size successive increments against the load each increment can serve. Compare the last block of panels, which may export much of its output, with spending that capital at a second site.
Storage and backup. Specify critical kW, usable kWh, transfer time and the minimum charge to reserve. Ask for a witnessed test under the required operating conditions. Energy reserved for an outage is unavailable for tariff arbitrage at the same time. A grid-connected solar installation alone gives no assurance that critical equipment will run through a grid outage.
Contracted supply. Compare an on-site power purchase agreement (PPA) with ownership and, where feasible, off-site supply through wheeling. A PPA shifts upfront expenditure into a purchase commitment. Check escalation, minimum purchases, exit costs and attribute ownership. For wheeling, confirm network eligibility, the applicable time periods, charges and crediting arrangements with the distributor. Eskom publishes its settlement arrangements and tariff schedules. [1–2]
Price the electricity the business can use
Build the baseline from the site’s actual tariff and invoice. Apply the relevant energy rate to each interval of avoided imports. Model fixed, network and demand charges separately, using the distributor’s charging rules. A site that still sets its monthly maximum demand after sunset may reduce daytime imports while paying the same maximum-demand charge. Municipal customers should use their own distributor’s schedule. [1]
A shift change that alters the investment decision
Consider a fictional R4.0 million array producing 1,000 MWh in year one. Assume each self-consumed kWh displaces R2.00, surplus earns zero, and annual operating costs are R150,000. Hold generation and the tariff constant to isolate one question: what happens if a major customer moves production to an evening shift?
At 80% self-consumption the site avoids buying 800,000 kWh, worth R1.60 million. After operating costs the annual benefit is R1.45 million, giving a simple payback of 2.76 years. At 50%, annual benefit falls to R850,000 and payback stretches to 4.71 years. The array produces exactly the same electricity in each case.
If the committee uses four years as an initial payback screen, annual net benefit must reach R1 million. Including operating costs, the site must use 575,000 kWh itself, or 57.5% of output. Operations can now answer a precise question about the order book and the shift plan. If it cannot support that threshold, price a smaller array and a phased installation.
Move from payback to a capital decision
Build a discounted cash-flow model over a common horizon. Include degradation, replacement, insurance, financing structure, tax treatment and residual or exit value. Match nominal cash flows to a nominal discount rate. Compare net present value (NPV), downside cash requirements and the opportunity cost of capital. For a PPA, run the same demand scenarios through the payment terms. Test a delayed start, lower daytime utilisation and different tariff escalation together. The illustrative payback above excludes these effects and uses no quoted market prices.
Give sustainability claims an evidence trail
Generation, consumption and emissions are three different records. Meter what the array produces, what the site exports and what it imports. For a battery, track charging source and losses. Then establish who owns the environmental attributes. If a third party takes the certificates, the site cannot also use those attributes to support its renewable electricity claim. The GHG Protocol Scope 2 Guidance sets out how certificate sales affect accounting and how contractual instruments are assessed. [3]
Before signing, ask the ESG lead to draft the sentence the company expects to publish. For “our sites consumed X MWh of renewable electricity”, specify the sites, period, meter records and evidence of attribute ownership and retirement where applicable. For a Scope 2 change, document the reporting boundary, applicable location-based and market-based calculations, factor source and vintage. A reduction in production can lower emissions even if the project underperforms. Explain that effect separately.
Bring the investment back to the executive table
At approval, freeze the business case, tariff version, load profile, reporting boundary and benefit owners. At commissioning, reconcile the meter readings and test the critical loads. After the first full billing cycle, finance should reconstruct what the same operating activity would have cost without the project. A year-on-year invoice comparison mixes changes in production, weather and prices with project performance.
Review exceptions quarterly. If generation is on plan but savings lag, compare actual daytime consumption with the shift plan before calling the installer. If savings are on plan but critical loads fail the outage test, the COO owns a continuity issue. If certificates are missing, ESG should hold the affected claim until the evidence reconciles. These are three distinct management decisions.
Across a portfolio, let the first sites change the next investment. Rank the next tranche by verified load overlap, strategic importance and downside NPV. A smaller roof at a facility the business intends to retain may deserve capital ahead of a larger roof at a site facing consolidation.
Emergent Africa’s perspective
Strategy defines the operating outcome and where capital should go. Decision intelligence connects meter data, tariffs and operating assumptions to the choices executives can make. ESG advisory connects the resulting claims to evidence. Put those disciplines around the same investment decision and the board can see what it bought, what changed and what to do next.
Investment committee decision sheet
Use at approval and revisit after the first full billing cycle.
1 Strategic fit | Executive sponsor
Which site, customer commitment or production constraint justifies the investment? State the expected site tenure and name the alternative use of capital. Record any non-negotiable continuity or emissions requirement.
2 Operational fit | COO and site manager
Show interval demand before and after planned efficiency measures. Mark the critical loads, their required operating duration and the test used to demonstrate continuity. Record the minimum daytime utilisation that supports the preferred option.
3 Financial exposure | CFO
Show base and downside NPV, peak funding need and contractual exit exposure. Identify the assumption most likely to reverse the decision. Set a threshold for redesign, phasing or deferral and assign someone to monitor it.
4 Reporting integrity | ESG lead
Specify the intended claim, reporting period, meter owner, emission factor and certificate rights. Agree who reconciles exports, records retirements and signs off the disclosure.
5 Benefits review | Executive sponsor and finance
Record the decision, conditions of approval, next review date and accountable executive. Compare actual net rand benefit, critical-load performance and evidenced renewable MWh with the approved case. Record the corrective action and owner for each material variance.
Sources and further reading
[1] Eskom Distribution. Tariffs and charges, including applicable schedules. www.eskom.co.za/distribution/tariffs-and-charges/
[2] Eskom Distribution. Wheeling. www.eskom.co.za/distribution/tariffs-and-charges/wheeling/
[3] GHG Protocol. Scope 2 Guidance, particularly chapter 6 and table 6.1. ghgprotocol.org/scope-2-guidance